Crusher exceeds expectations at Hunua

General
THE first Metso HP4 crusher installed in Australasia has achieved impressive crushing efficiencies and increased capacity at Winstone Aggregates’ Hunua Quarry.
The crusher was supplied by Mimico and installed during the Easter shutdown period this year.
Winstone Aggregates national manufacturing manager Jason Lowe says the new generation crusher is achieving or exceeding all the performance targets set by the company. He says the original tertiary crusher was still running well, but struggled to adapt to a shift in market requirements.
“We found that more of our customers, especially the readymix concrete and asphalt customers, were tending to go with smaller chip sizes. So we were seeing increased demand, especially for 10mm chip.
“Our existing crusher was making too much 19mm and we had to recirculate the 19mm to get more 10mm. As a result of this extra load in the tertiary circuit, our throughput was limited, the crusher was working at full capacity and therefore the overall crushing circuit was not as efficient as we wanted,” says Lowe.
The crusher was operating 18 hours a day, six days a week, with the rest of the time required for preventive maintenance – giving minimal flexibility to adjust to market demands.
Winstone Aggregates have utilised Metso’s Bruno process simulation software for many years and staff began modelling the existing process using Bruno about three years ago. They modelled the existing process and calibrated it against actual measured inputs and outputs. Then they produced a number of Bruno models incorporating the Metso HP4, liaising with Mimico’s process equipment engineer David McCaffrey and Metso in Australia.
Lowe says the new generation HP4 was the only crusher seriously considered. For a start, the HP4’s compact nature meant it was the only viable crusher that could fit the space vacated by the existing tertiary crusher. “And it was also the only crusher I had confidence in to give us the advantages we needed,” says Lowe. “If the HP4 had not been available, we would have most likely continued with what we had.”
The crusher was delivered within two weeks of purchase. Excellent planning meant it was installed over a five day Easter shutdown period and was operational for the scheduled plant restart. The crusher met all of its agreed performance targets, and Metso’s performance guarantee testing was conducted, completed and signed off on the same day.
“We found Mimico were extremely flexible in the range of purchase options available, and their backup was first class. I could tell straightaway that Mimico were as excited and committed to this project as we were and that gave me additional confidence that the project would be a success,” says Lowe. “For example, we had their top service technician dedicated to the project before, during and for two weeks after installation, to ensure there were no issues.”

Winstone Aggregates has also agreed to a parts supply agreement with Mimico, meaning that the service and aftercare of the HP4 will continue for at least five years.
Production improvements measured as part of the Metso performance guarantee have exceeded expectations being better than the Bruno predicted improvements which are shown below:
Tertiary Throughput ……….+22%
PAP …….………….….+19%
10mm  …….…………….+31%
Lowe says the improvements mean the tertiary plant can now do greater tonnage in fewer hours, giving Hunua the capacity to increase production to meet market demand. A benefit they’ve not been slow to take advantage of.
“We have already taken on contracts requiring significant volumes of 10mm concrete chip because of the production improvements. Without installing the HP4, we would not have been able to take on that work.”
Apart from improved crushing performance, the HP4 features thicker liners that are replaced less frequently. Changing liners also requires less labour and downtime because they don’t require backing material. The Winstone Aggregates HP4 was also supplied with the advanced automation package that displays the liner wear rate, crusher settings and key operating parameters, ensuring optimal performance and timing of scheduled maintenance to maximise crusher uptime.
Ironically, Winstone Aggregates began justifying the HP4 purchase based on extra crushing capacity and projected growth. When the recession bit, the justification was recalculated on improved crushing efficiencies. Either way, the HP4 measured up.

 

 Contact: stefan@cranesales.co.nz

 

Publishing Information
Page Number:
1
Related Articles
Vertical Horizonz opens centre of excellence in Papakura
Vertical Horizonz held the official opening of its new centre of excellence for access trades in Papakura recently. At 4,000 square metres, the new centre will be one of the largest training...
New Autodesk AI capabilities
Autodesk has unveiled new ways it is bringing Autodesk AI-powered capabilities to Autodesk Fusion and Alias, designed to increase productivity as the manufacturing industry delivers increasingly...
Emerging Director Award winner ready for next step
South Otago director Kate Faulks will receive an Institute of Directors (IoD) Emerging Director Award. Kate Faulks has an MBA in chemical engineering, and a Wonder Project Ambassador for Engineering...